Phase One of I-90 Construction Project Nears Completion

The below information came from an Illinois Tollway press release. 

The Illinois Tollway will begin the process of returning traffic to the newly constructed eastbound side of the Jane Addams Memorial Tollway (I-90) between Rockford and Elgin next week as the first phase of the $2.2 billion I-90 Rebuilding and Widening Project nears completion for this construction season. 

In addition, eastbound traffic will be shifted Sunday night (Oct. 6) at the Marengo Toll Plaza on I-90 requiring a temporary reduction in the number of open road tolling lanes.    

Find out what's happening in Huntleywith free, real-time updates from Patch.

Eastbound traffic between I-39 in Rockford and the Elgin Toll Plaza has been traveling on the westbound side of the road since spring to accommodate the rebuilding and widening of the eastbound lanes. The westbound lanes in this segment are scheduled to be rebuilt and widened in 2014, and work on the segment of I-90 from Elgin to Chicago is scheduled for 2014-2016.

 

Find out what's happening in Huntleywith free, real-time updates from Patch.

“We’ve made tremendous progress this construction season, and we’re pleased to report that we’re on schedule to complete the western section of I-90 next year,” said Illinois Tollway Executive Director Kristi Lafleur. “This return to normal traffic patterns allows us to prepare for the winter break in construction.” 

 

Traffic shifts will be scheduled throughout October on I-90 to return traffic to the eastbound side in remaining sections between Rockford and Elgin. Once completed, traffic will remain in this configuration over the winter, however, work will continue in the median to prepare for the rebuilding and widening of the westbound lanes in 2014.

 

I-90 Mainline Traffic Shifts

Next week, traffic shifts are scheduled in a 7-mile section near Elgin and a 5-mile section near Belvidere, as well as at the Marengo Toll Plaza. Eastbound I-90 traffic will be shifted from the westbound side of the road onto new pavement on the eastbound lanes with a full right shoulder.

 

On the east end near Elgin, two lanes of traffic will be moved back onto the eastbound side between Brier Hill Road and the Union Pacific Railroad overpass near Elgin. On the west end of the project near Belvidere, two lanes of traffic will be moved back onto the eastbound side between the Union Pacific Railroad underpass and Tripp Road.

Work to shift mainline traffic is scheduled to begin at 6 p.m. on Monday, October 7, in both sections, reducing traffic to a single lane overnight. The lane reduction and traffic shifts will be completed by 5 a.m. on Tuesday, October 8, in advance of the morning rush hour.

Marengo Toll Plaza Traffic Shift

Eastbound traffic will also be shifted next week at the Marengo Toll Plaza, requiring a temporary reduction in the number of open road tolling lanes. The eight-week closure is necessary as work continues to rebuild and widen the eastbound lanes between Rockford and Elgin.

 

At 10 p.m. on Sunday, October 6, one open road tolling lane will close for the traffic shift. When work is completed by 6 a.m. on Monday, October 7, eastbound traffic at the Marengo Toll Plaza will be shifted to the right and one of two open road tolling lanes will be closed for eight weeks to provide a work zone so the left shoulder and left lane can be rebuilt.  

 

During this time, one open road tolling lane will remain open and a temporary I-PASS Only lane will be available on the cash collection side of the toll plaza to provide an additional non-stop option for I-PASS customers. In addition, two cash lanes with toll collectors will remain in place and all lanes will accept I-PASS. 

 

Some delays are expected during peak hours and drivers are encouraged to use the I-PASS Only lane on the cash side of the plaza when traffic is heavy. In addition, depending on the destination, traffic travelling east toward Chicago and O’Hare International Airport can use I-39 to the Reagan Memorial Tollway (I-88) as an alternate route.

 

Once the work on the left side of the eastbound lanes at the Marengo Toll Plaza is complete, two open road tolling lanes will be restored and construction will continue with work to rebuild the right shoulder and lane.